Our Approach
Our paving team began by excavating the failed 30' x 3' section to a depth of 5 inches, ensuring all unstable organic material and debris were removed off-site. We engineered a new foundation by installing 3 inches of 2A modified stone, which was mechanically tamped to create a high-density, compacted base. We then applied 2.5 inches of premium 9.5mm top-grade asphalt, tamping for maximum compaction and a flush finish. The project concluded with a hot-tar application to the seams, creating a watertight bond between the new patch and the existing pavement.